3 THE FACTORY OVERVIEW
19
• • • • •
adequate materials will be available. The process plan for Handlebar is summarized
below.
Handlebar Plan
N
ECK
P
OST
The process plans for a handlebar contain four operations: cut, machine, bend, and finish.
The completed neck post is then placed in inventory to be used by orders for handlebar
assemblies. The raw materials required at the cut operation have not been included in the
process plan as the material-planning replenishment process at the MRP level assures that
adequate materials will be available. The process plan for Neck Post is summarized below.
Neck Post Plan
Seq
#
Operation
Work Cell
Setup
Time
Process
Time
Additional
Resources
Notes
10 Cut
Handlebar
Tubing
Cut 0.16 0.055
20 Bend
Handlebar
Tubing
Bend BM 0.043
30 Finish
Handlebar
Finish 0.14 0.088 Place in inventory
10
CUT
HANDLEBAR
TUBING
20
BEND
HANDLEBAR
TUBING
30
FINISH
HANDLEBAR
Seq
#
Operation
Work Cell
Setup
Time
Process
Time
Additional
Resources
Notes
10 Cut Neck
Post
Cut 0.21 0.065
20 Machine
Neck Post
Machine MM 0.120
30 Bend Neck
Post
Bend BM 0.072
40 Finish Neck
Post
Finish 0.14 0.074 Place in inventory
10
CUT NECK
POST
20
MACHINE
NECK POST
30
BEND NECK
POST
40
FINISH NECK
POST